§ 54-251. Completion of on-site improvements required prior to plat approval.  


Latest version.
  • Except as provided in this article, all on-site improvements required by this chapter, other than a private road serving a family subdivision, shall be completed prior to approval of the final plat. Prior to approval of the final plat:

    A)

    The subdivider shall submit to the agent a certificate of completion of all of the improvements prepared by a professional engineer or a land surveyor, to the limits of his license; and

    B)

    The subdivider shall certify to the agent that all of the construction costs for the improvements, including those for materials and labor, have been paid to the person constructing the improvements.

    (Res. No. 10-01, § c, 6-14-2011, eff. 8-1-2011)